Ongoing Roads Project in Nairobi to be Complete by October

The Nairobi Regional Development Implementation Coordination Committee (RDICC) is determined to unblock all bottlenecks of the national government projects that are delaying the completion of ongoing government projects in the county.
The Committee led by the Nairobi County Commissioner Flora Mworoa during a site visit of the 17.2 Km road project funded by the Kenya government in collaboration with the European Union at a cost of Ksh. over 4.5 billion said the works has stalled for over three years in some roads due to encroachment of road reserves, court injunction related to land acquisition, traders occupying walkways and mechanics turning Gikomba road into a garage.
The committee members who also included the Committee’s Secretary, Mr. Humphrey Ngunjiri from the Presidential Delivery Unit said the project that commenced on May 2014 was expected to be complete in November 2016.
Members recommended that Kenya Urban Roads Authority (KURA) sets a budget for doing the roads that have challenges as the contractor proceeds with roads that have no problem, and gave the contractor, Reynolds Construction Company Ltd up to October to this year to complete the project.
Ms. Mworoa said the government will ensure that all public land in the county is used for the intended purpose and cautioned members of the public against encroaching and engaging in illegal acquisition of public land.
“For the project to meet the deadline I urge the contractor to continue with the work in other parts while the issues stalling the projects are sorted out,” said Ms. Mworoa.
She commended KURA for the good works done on the Muratina Street road in Mathare area that links First Avenue, Thika Road, Eastlands and General Waruinge road and urged motorists to utilize the road to decongest other roads.
Mr. Humphrey said the main purpose of constructing the roads was to decongest roads in Westlands, Thika Road and Industrial Area, and to enhance Limuru road, and if the Deep Sea problem and the land acquisition issue both in Westlands are not resolved the project will not have achieved the intended purpose.
He told KURA to initiate another financing agreement for doing the roads that have been omitted in the ongoing contract due to the hurdles the contractor is encountering.
Engineer Priscillah Ngetich from Kenya Urban Roads Authority said KURA has omitted the Accra Road Extension due to a sewer line problem, Ring Road Parklands Extension to Thika Road due to encroachment of a road reserve and the quarry road that has been turned into a garage.
“Obstacles created by informal settlement and court cases has made the former design of the Interchange Likoni-Enterprise road to change from an underpass to overpass to avoid a lot of land acquisition and drainage issues,” said Ms. Ngetich.
Lusaka road is complete while Muratina Street and its extension to Thika road is 97 percent complete, Likoni Road is 95 percent complete, Enterprise Road Extension (Homabay road Junction to Likoni road) is 91 percent complete, Interchange Likoni/Enterprise is 75 percent complete while Ring Road Parklands to Limuru Road is 57 percent complete.
The contractor assured the committee that the project will be complete by October since the outstanding payments has been settled.
The committee said it will evict all individuals who have encroached the road reserves to meet the deadline of the project.
The committee was informed that influence from Amnesty International who have been defending the Deep Sea Slum resident has been the major cause of delay in the completion of the road, a matter causing the government to incur more expenditure in maintaining the contractor.
The delay has caused a variation of the value of the whole project from the initial Sh. 4.5 billion to Sh. 5.4 billion.